![](https://pdfstore-manualsonline.prod.a.ki/pdfasset/a/9e/a9ecdf29-f269-455b-bf2a-9e0fc2a92449/a9ecdf29-f269-455b-bf2a-9e0fc2a92449-bgc.png)
Rev. M
SECTION 3
INSTALLATION AND OPERATION
WARNING
INSTALLATION, SERVICE, MAINTENANCE OR OPERATION SHOULD
BE PERFORMED BY QUALIFIED PERSONNEL ONLY.
3.1 INSTALLATION
All CSC units are supplied ready for operation with all ordered options installed.
When properly connected, no electrical adjustments should be necessary prior to use.
3.1.1 Location
The CSC may be installed in all locations meeting the environmental requirements as
specified in paragraph 1.2.4.3 except where explosive or highly corrosive
atmospheres may be present. The equipment should be accessible to qualified
personnel only. In addition, adequate drainage should be provided to preclude the
possibility of standing water hindering maintenance or normal operations.
3.1.2 Power Requirements
Standard model CSC units require a source of 120 VAC at 50/60Hz. If the particular
unit to be installed is equipped with option -2, a source of 220 to 240 VAC at
50/60Hz is required. Refer to Table 1-1.
3.1.3 Detail Installation Checklist
NOTICE: (1) Read and become familiar with this procedure before
attempting installation of this equipment. Improper
installation procedures can damage this equipment and may
void the warranty!
(2) Further, the instructions for each equipment option included
should similarly be understood before proceeding with
installation.
(3) Installer should initial in space provided ( ) after completing
each step.
3.1.3.1 Mechanical Installation
( ) 1. Unpack the CSC, open the enclosure and check for any
shipping damage.
( ) 2. Remove the dead front cover from the high voltage section.
6