56 HP BladeSystem p-Class Enclosure Installation Guide
Full rack 42U solution with two pairs of mini bus bars
Observe the following additional guidelines for configuring a full-rack 42U
solution with two pairs of mini bus bars:
Set the power configuration switches to establish the two power zones.
Cable the power management module in zone 2 (upper pair of mini bus bars)
to both adjacent server blade management modules, above and below. This
connection enables system management to establish a full rack topology.