6. Attach process fluid supply and return piping to the coil. Standard field
piping connection is an NPT male connection at the coil. A flanged
connection requires a gasket between the fluid cooler and the fluid
supply piping.
Forweldedconnectionsprotectadjacentareasfromexcessiveheat
andsparksordamagemayoccur.
7. Wire motor(s) and recirculation pump(s) in accordance with wiring
diagram.
For maintenance/safety purposes, SPX Cooling Technologies recom-
mendsalockouttypedisconnectswitchforallmechanicalequipment.
In addition to a disconnect switch, the motor should be wired to main
power supply through short circuit protection, and a magnetic starter
with overload protection.
Motor Wiring
Wire motor leads as shown on the motor nameplate matching the supply
voltage.Donotdeviatefromthemotornameplatewiring.
Either of following symbols may be shown on the motor nameplate
Δ, Δ Δ
, Y, or YY. These symbols represent how the motor is constructed on
theinsideandinnowayhaveanythingtodowithaDeltaorWyeelectrical
distribution system serving the motor.
When using a starter:
• Setmotoroverloadprotectionto110%ofmotornameplateamps.
This setting allows the fan motor to operate during cooler weather.
Duringcoolerweatheritiscommonforthemotortodraw6to
10%higherthannameplateamps.Highampsarecommonduring
tower commissioning when the tower is dry and the ambient air
temperature is cool.
• Donotstartthemotormorethansix times per hour. Short cycling
the tower will cause fuses, breakers or O.L.s to operate and will
decrease motor life.
Caution