INSTALLATION STEPS
The following steps are required to install the Total Access 1248. Each step has an associated
procedure which is referenced below the step. Each procedure provides detailed information
for completing the step.
1. Mount the Total Access 1248 system with the appropriate hardware.
For detailed information, refer to “Mounting the Total Access 1248” on page 3-5.
2. Ground the Total Access 1248.
For detailed information, refer to “Ground Connection” on page 3-8.
3. Make the power connections to the Total Access 1248.
For detailed information, refer to “Power Connection” on page 3-9.
4. Connect the Ethernet cable to the Total Access 1248.
For detailed information, refer to “Ethernet Connection” on page 3-11.
5. Connect the DB-15 male alarm cable connector to the Total Access 1248 and wire-wrap
the connections to an alarm panel.
For detailed information, refer to “Alarm Connections” on page 3-12.
6. Connect the network cable.
For detailed information, refer to “Network Connections” on page 3-13.
7. Connect the ADSL2+ plus POTS and POTS cables.
For detailed information, refer to “ADSL2+ Plus POTS Connections” on page 3-14.
8. Turn-up the Total Access 1248.