A SERVICE OF

logo

65
Relief Devices
Fusible plugs are located in each cir-
cuit to protect against damage from excessive pressures.
HIGH-SIDE PROTECTION One device is located
between condenser and filter drier; a second is on filter drier.
These are both designed to relieve pressure on a temperature
rise to approximately 210 F (99 C).
LOW-SIDE PROTECTION A device is located on suc-
tion line and is designed to relieve pressure on a temperature
rise to approximately 170 F (77 C).
PRESSURE RELIEF VALVES (208/230, 460, 575 v;
60 Hz Units Only) Valves are installed in each circuit (one
per circuit). The valves are designed to relieve at 450 psig
(3103 kPa). These valves should not be capped. If a valve
relieves, it should be replaced. If valve is not replaced, it may
relieve at a lower pressure, or leak due to trapped dirt from the
system which may prevent resealing.
The pressure relief valves are equipped with a
3
/
8
-in. SAE
flare for field connection. Some local building codes require
that relieved gases be removed. This connection will allow
conformance to this requirement.
Other Safeties
There are several other safeties that are
provided by microprocessor control. For details refer to
Alarms and Alerts section on page 48.
PRE-START-UP
Do not attempt to start the chiller until following checks
have been completed.
System Check
1. Check all auxiliary components, such as the chilled
fluid circulating pump, air-handling equipment, or
other equipment to which the chiller supplies liquid.
Consult manufacturers instructions. If the unit
has field-installed accessories, be sure all are properly
installed and wired correctly. Refer to unit wiring
diagrams.
2. Backseat (open) compressor suction and discharge shut-
off valves. Close valves one turn to allow refrigerant pres-
sure to reach the test gages.
3. Open liquid line service valves.
4. Fill the chiller fluid circuit with clean water (with
recommended inhibitor added) or other noncorrosive flu-
id to be cooled. Bleed all air out of high points of system.
An air vent is included with the cooler. If outdoor temper-
atures are expected to be below 32 F (0° C), sufficient in-
hibited ethylene glycol or other suitable corrosion-inhibit-
ed antifreeze should be added to the chiller water circuit
to prevent possible freeze-up.
5. Check tightness of all electrical connections.
6. Oil should be visible in the compressor sight glass. See
Fig. 35. An acceptable oil level in the compressor is from
1
/
8
in. to
3
/
8
in. of sight glass. Adjust the oil level as re-
quired. No oil should be removed unless the crankcase
heater has been energized for at least 24 hours. See Oil
Charge section on page 53 for Carrier-approved oils.
7. Electrical power source must agree with unit nameplate.
8. Crankcase heaters must be firmly locked into compres-
sors, and must be on for 24 hours prior to start-up.
9. Fan motors are 3 phase. Check rotation of fans during the
service test. Fan rotation is clockwise as viewed from top
of unit. If fan is not turning clockwise, reverse 2 of the
power wires. For low noise fan option on 50 Hz chillers,
fans rotate counterclockwise as viewed from top of unit.
If fan is not turning counterclockwise, reverse 2 of the
power wires.
10. Check compressor suspension. Mounting rails must be
floating freely on the springs.
11. Perform service test to verify proper settings.
IMPORTANT: Before beginning Pre-Start-Up or Start-
Up, complete Start-Up Checklist for ComfortLink
Chiller Systems at end of this publication (page CL-1).
The Checklist assures proper start-up of a unit, and
provides a record of unit condition, application require-
ments, system information, and operation at initial
start-up.
*Lead compressor only.
Fig. 35 Compressor Connections
(Lead Compressor Shown)